CLOUDLINK
Installing a Cloudlink is optional.
Ensure that the Cloudlink model is always compatible, older models need to have the RS485 comms enabled at the factory. Please make sure firmware is up to date on the Inverter and Cloudlink
The Cloudlink will connect to the Battery via:
Cloudlink’s (Serial/RJ12 Port) to the Battery (RS232/RJ12 Port)
(Black Cable) – RJ12 to RJ12 (450mm) cable.
RJ45 PIN LAYOUTS
The Deye Inverter will connect to the Battery via:
Inverter (CAN Port) to Battery (CAN Port)
Straight RJ45 to RJ45 wire - 1500mm.
Ensure that the clip is pointed away from you when counting the pins.
DEYE – 5kW / 8kW / 16kW (DUAL PORT)
*Please note that Cloudlink communication with a DAUL PORT Inverter requires a second RJ45 cable that connects PIN 7 & 8 from Inverter (RS485) to Cloudlink (MUL/RS485).
Pin | Inverter | X-101/AM-4/AM-2 | AM-5/AM-10 | Blade | Cloudlink |
1 | - | - | - | - | - |
2 | - | GROUND | - | - | - |
3 | - | - | - | - | - |
4 | CANH | CANH | CANH | CANH | CANH |
5 | CANL | CANL | CANL | CANL | CANL |
6 | - | - | - | - | - |
7 | - | - | - | - | RS485 A |
8 | - | - | - | - | RS485 B |
DEYE – 8kW / 10kW / 12kW (SINGLE PORT)
Pin | Inverter | X-101/AM-4/AM-2 | AM-5/AM-10 | Blade | Cloudlink |
1 | - | - | - | - | - |
2 | - | - | - | - | - |
3 | - | - | - | - | - |
4 | CANH | CANH | CANH | CANH | CANH |
5 | CANL | CANL | CANL | CANL | CANL |
6 |
| GROUND | - | - | ACTIVE |
7 | - | - | - | - | ACTIVE |
8 | - | - | - | - | ACTIVE |
4 & 5 Pin Layout image reference seen below:
2, 4 & 5 Pin Layout image reference seen below:
7 & 8 Pin Layout image reference seen below:
4, 5 & 6 Pin Layout image reference seen below:
4, 5, 6, 7 & 8 Pin Layout image reference seen below:
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article